In accordance with clause 16.1 of the NEC3 Engineering and Construction Contract, the Issuer hereby gives early warning to the Recipient of a matter which could:
- Increase the total of the Prices
- Delay Completion
- Delay meeting a Key Date
- Impair the performance of the works in use
Description of the matter:
[Describe the issue, its likely cause and the works affected.]
A risk reduction meeting is proposed in accordance with clause 16.2 on [date / at the next scheduled meeting].
The parties will co-operate in considering how the effect of the matter can be avoided or reduced (clause 16.3).