Action checklists · NEC3 ECC

From clause to action, one tick at a time.

Each checklist turns a single NEC3 clause into the concrete steps the responsible party must take — what to include, when to act, and what to keep on file. Start with the Clause 31 programme submission below.

Clause 31

First programme submission

Responsible: Contractor (submitting to the Project Manager)

Trigger

No programme is identified in Contract Data part two, OR a new first programme is required.

Deadline

Within the period stated in Contract Data part one for submission of a first programme after the Contract Date (clause 31.1).

If missed

If a first programme is not submitted, one quarter of the Price for Work Done to Date is retained in assessments until it is submitted (clause 50.3).

Key dates and milestones (31.2)

Every programme submitted for acceptance must clearly show the contractual dates and the planned dates derived from them.

Order, timing and interfaces (31.2)

Demonstrate how the works will be sequenced and how third parties interface with the programme.

Float, risk and procedures (31.2)

The programme must be realistic — including time risk allowances and the contract's own procedures.

Method statement per operation (31.2)

Each operation needs a statement of how the work will be done — not just when.

Submission and acceptance loop (31.1 & 31.3)

Get the programme in on time and address common reasons for non-acceptance up front.

Reference: NEC3 Engineering and Construction Contract, clauses 31.1–31.3 and 50.3. This checklist is a working aid and does not replace the contract or professional advice.